From the initial planning stages to the installation and finishing touches, a bathroom renovation encompasses several phases. If you're embarking on this task for the first time, estimating the duration of each stage can be challenging. So, how long does a bathroom renovation typically take in Sydney, and what are the critical steps involved in the process?
RENOVATION TIME FRAMES, WHAT YOU NEED TO KNOW
While a bathroom renovation is both thrilling and advantageous, it can disrupt your daily routine if you don't have another bathroom. A general idea of the expected timeline is essential for preparation and planning. The more thorough you are in this regard, the more efficiently the project will progress, allowing you to savour your fresh bathroom sooner.
At Aussie Bathroom Renovations, we typically complete a bathroom renovation in approximately 3 to 6 weeks, on average. These estimates do not encompass the time spent on planning, project quoting, and selecting style elements for your new bathroom, among other pre-construction tasks.
LET'S START BREAKING DOWN THE RENOVATION It's essential to understand that these figures are general guidelines and averages, as each bathroom renovation project is influenced by a unique set of factors, including: 1.The size of your bathroom. 2.The extent of demolition required, such as removing walls or relocating windows. 3.Whether existing plumbing lines are being utilised. 4.The complexity and availability of the chosen materials. 5.Coordination of various tradespeople. 6.Unforeseen events that may impact the project timeline. Before embarking on your bathroom renovation journey, it's beneficial to have a basic understanding of the sequence of events and the duration of each stage of your renovation.
THE STAGES OG A BATHROOM RENOVATION!
Planning and Development:
1.Research and select a bathroom style.
2.Visit Showrooms for inspiration or schedule a Free Design Consult and Quote with our expert design team.
3.Your consultant will gather project details, style preferences, functionality requirements, and budget to prepare a quote.
4.After accepting the quote, a construction contract will be drafted, and a project timetable will be established.
5.Discuss responsibility for picking and ordering fixtures like tiles, tapware, and vanities to ensure they arrive on-site before the start date.
6.The processing time for permits and approvals can vary, particularly when planning a significant bathroom renovation. We ensure that all necessary documentation is meticulously prepared in accordance with specific requirements to mitigate potential delays.
7.Planning, approvals & research can take four weeks to several months.
Demolition:
1.Removal of the existing bathroom typically occurs swiftly once tradespeople begin.
2.Demolition usually takes 1 to 2 days.
3.Asbestos testing may add 1 to 2 days if professional removal is required.
Groundwork:
1.Carpentry and structural work may involve the installation of new structural beams to support wall changes or new windows, taking 1-2 days, depending on the scope.
2.Plumbing and electrical "rough-in" includes the placement of plumbing points in walls and floor wastes, along with wiring for power points, exhaust fans, lighting, etc., and this takes 1-2 days.
3.Gyprock sheeting of walls and ceilings usually requires 1-2 days.
4.Waterproofing and tiling, including laying a cement screed for tile installation, waterproofing with a liquid rubber membrane, and tiling, may take up to 7 days, considering drying times.
Fit-Off and Painting:
1.Plumbing and electrical fit-off involve connecting chosen items like toilets, baths, basins, tapware, and showers and completing drainage under the floor, taking 1-3 days.
2.Electricians install light fixtures, switches, heated towel rail and extractor fan.
Cleaning:
1.Professional cleaning to remove construction debris, dust, and waste typically requires one day.
Delivery of Your Dream Bathroom:
1.You can now enter your newly renovated, fully functional bathroom and personalise it to reflect your unique style. Whether your bathroom is spacious or compact, selecting chic accessories, greenery, art pieces, towel hooks, and toilet paper holders will add the finishing touches to your makeover.
COMPLETED BATHROOM Considering factors like your bathroom's size, approval processing times, and the availability of products and tradespeople, you can anticipate that a complete bathroom renovation will typically span 3 to 12 weeks. More intricate projects lean towards the longer end of this range. Regardless of the duration, the outcome will be well worth it, as you'll relish an upgraded bathroom that enhances your contentment and well-being while adding value to your property.
Talk to our friendly bathroom experts today about your Sydney bathroom renovation.
GET IN TOUCH
Talk to our friendly bathroom experts today about your Sydney bathroom renovation.
Builder's License: 285398C
© 2020 Aussie Home Renovations. All Rights Reserved. Website by Primomedia.